PROJECT PROGRESS UPDATE: NAM SUM - NONG CONG 220KV POWER LINE REACHES 99% COMPLETION
As of June 11, 2024, NVETC 's construction progress at the Nam Sum Substation has reached 99% completion of the main items.

The 220kV Nam Sum - Nong Cong power line project has reached 99% completion.
The 220kV Nam Sum – Nong Cong transmission line project is one of the cross-border energy projects, playing a key role in relieving power congestion and transmitting and importing electricity from Laos to Vietnam. Accordingly, Nam Viet Energy Technology Co., Ltd. is honored to be the unit trusted by the investor, WANG INVESTMENT SOLE CO., LTD., to implement the project. Nam Viet is focusing its maximum resources to ensure that the installation and commissioning work is completed on schedule. As of June 11, 2024, the project has completed 99% of the work.

Projects Completed by NVETC
In this project, Nam Viet 's team of engineers and workers have completed the work. The core components include:
+ Construction and installation work;
+Testing, calibration, and adjustment of relays.
+The procedures for energizing and commercial operation have been planned and are ready to facilitate electricity imports.
Upcoming Work Items
In the coming period, the Nam Viet team will continue to exchange information with relevant parties, preparing for the implementation of the remaining items and completing the project to import electricity from Laos to Vietnam. This will strengthen the friendly cooperation in the energy sector between Vietnam and Laos.