The latest project news and events from NVETC.
NVETC repairs and restores the systems and equipment of Sao Va Hydropower PlantOn 21 July 2026, NVETC’s engineers completed the final tests and acceptance and officially handed over the whole plant under the Sao Va Hydropower Plant restoration project.
NVETC sets up the Operation Control Center (OCC) for the Nam Vao hydropower clusterOn 9 July 2026, NVETC completed the establishment of the Operation Control Center (OCC) for the Nam Vao hydropower cluster.
COMPLETION OF PERIODIC TESTING PROJECT AT NAM SI LUONG 3 & 4 HYDROELECTRIC POWER PLANTIn October 2025, the NVETC team completed the periodic testing project for electrical equipment at the Nam Si Luong 3 & 4 Power Plant.
NVETC IS A PARTNER PROVIDING EQUIPMENT AND TECHNICAL SOLUTIONS FOR THE DAK PONE HYDROELECTRIC PROJECT.Nam Viet Energy Technology Co., Ltd. (NVETC) is proud to be the equipment and technical solution provider for the Dak Pone Hydropower Plant Project.
NVETC installs, tests and energises the 220kV Nam Sum 1A Switching Station for COD handoverIn December 2024, NVETC completed installation, testing, calibration and COD handover for the 220kV Nam Sum Switching Station – Nong Cong transmission line project.
PROJECT PROGRESS UPDATE: NAM SUM - NONG CONG 220KV POWER LINE REACHES 99% COMPLETIONAs of June 11, 2024, NVETC 's construction progress at the Nam Sum Substation has reached 99% completion of the main items.NVETC’s engineers are ready to survey your site and propose the right solution.