NVETC replaces the DCS and protection systems at Bac Binh Hydropower Plant
NVETC delivered the full EPC scope — design, supply and installation — to replace the entire control and monitoring system (DCS) and the protection relays at Bac Binh Hydropower Plant.
1 / 5
Building on a series of successes in delivering solutions and engineering services, NVETC has again demonstrated outstanding capability by carrying out the full EPC scope — design, supply and installation — to replace the entire control and monitoring system (DCS) and the protection relay system of Bac Binh Hydropower Plant.
Bac Binh Hydropower Plant, with a capacity of 33MW (Phan Son Commune, Lam Dong Province), is the downstream cascade plant of Dai Ninh Hydropower Plant and operates its reservoir on a daily regulation basis. The plant has been in operation since 2009, with Vietnam Power Development Joint Stock Company (VNPD) as the investor. Besides its main task of generating electricity, Bac Binh Hydropower Plant also supplies irrigation and domestic water to the downstream area and helps cut, reduce and delay floods downstream.
To best serve these tasks, fit the maintenance schedules of both the Dai Ninh and Bac Binh hydropower plants and make efficient use of water resources, NVETC worked with VNPD’s staff to dismantle the old system and install the new one within a record outage window:
- From 26 June to 10 July 2026: 15 days for Unit 1
- From 17 July to 31 July 2026: 15 days for Unit 2, the substation and auxiliary power (substation outage from 22:00 on 24 July to 15:00 on 27 July).
YCON Software is the core software for SCADA/DCS/OCC systems, researched and developed by NVETC. Integrated with advanced equipment from around the world, the system gives Bac Binh Hydropower Plant an optimal control and protection solution that fully meets the strict technical standards of EVN and the Ministry of Industry and Trade.
NVETC also provided thorough, detailed training, technology transfer and support for VNPD’s technical staff, so that VNPD can fully master the new system without depending on any outside party for operation, maintenance, or changes to configuration and parameters when needed. In addition, NVETC carried out AGC function tests with NSMO and worked with the excitation system supplier to test the AVC function as required.