On May 23, 2024, Nam Viet Energy Technology Co., Ltd. conducted periodic testing and inspection of the electrical system at Tan My 2 Hydropower Plant.
1 / 3NVETC Completes Trial of Tan My 2 Hydropower Plant
In May 2024, NVETC officially completed the periodic inspection, maintenance, testing, and technical safety certification of electrical equipment for the Tan My 2 hydropower plant in Ninh Son District, Ninh Thuan Province.
Factory Experiment Scale

Nam Viet Energy Technology Co., Ltd. has conducted periodic testing and inspection of the electrical system of Tan My 2 Hydropower Plant, specifically the following items:
- Conduct periodic testing of equipment: transformers, voltage transformers, current transformers.
- Regularly inspect equipment: circuit breakers, power cables, surge arresters, disconnectors.
- Experimenting with the secondary relay circuit of the generator sets.